Sakhalin 2

Sakhalin IISakhalin 2, Phase II Pipelines Project for Sakhalin Energy Investment Company (SEIC) was an extremely complex and challenging project on a number of levels: political, environmental, cultural, regulatory, topography, geophysical, weather, etc.  Further difficulties were added by the sizable scope of work and contractual and organizational arrangements devised by the protagonist:

The onshore oil and gas pipelines run from Piltun in the north of Sakhalin Island via the Onshore Processing Facility (OPF), near Lunskoye, to Prigorodnoye, in the south. The two pipeline systems each cover a distance of over 800 km, including 126 km of swamp crossings, 110 km over mountainous routes, more than 1,000, mainly small but sensitive, river crossings, 18 rail crossings, 10 road crossings, and 21 seismic fault crossings. The distance from the Piltun landfall to the OPF is 172 km (pipeline diameters in this part of the route are 20 inch for both the oil and the gas line). The distance from the OPF to the Liquefied Natural Gas/Oil Export Terminal (LNG/OET) plant is 637 km (pipeline diameters in this part of the route are 24 inch and 48 inch for the oil and gas line respectively). Two Short multiphase pipelines (30 inch diameter, onshore length 7 km) and a 4-inch Mono-Ethelyne Glycol - MEG – pipeline in the same right-of-way connect the landfall at Lunskoye to the OPF.  The scope included a Gas Distribution Terminal (GDT) approximately 18 pigtraps and 160 block valves of various diameters, high voltage electric cables and fibre optic cables.

Starstroi was awarded the EPC contract and with Saipem operated as a management contractor but had contractual arrangements with Lukoil and Spiecapag. The pipeline route was divided into 4 sections from north to south 272kms, 175kms, 160kms, and 190kms and construction completed by 7 Russian pipeline subcontractors with a combined workforce totalling over 5,000 workers.

The project was theoretically very much constrained by stringent Russian Federation environmental and industrial regulations but there were many and consistent breaches by Russian pipeline construction subcontractors, which was a major challenge for SEIC and its expat supervisory workforce.

I was hired initially as a Company Site Representative to take over spreads 1A and 1B from Chaivo to the OPF, Starstroi and its subcontractors were not complying with project objectives regarding HSE and Quality and schedule performance was also poor but with good management I was able to restore these requirements to a satisfactory level and increase productivity. My methods of management aimed at the winter program of river crossings was highly appreciated and adopted by the other sections. When the contract changed from EPC to Cost reimbursable in 2006, I was transferred to Section 4 and took over running of the subcontractor as Construction Manager. I was able to develop a good working relationship with the Russian pipeline construction subcontractor and quickly gained their respect and within a short period of time they were performing in a cooperative manner according to the terms and the spirit of their contract.  

Other Case Studies

Map
The Baku, Tbilisi, Ceyhan (BTC) pipeline is a large diameter, long distance pipeline (1,768 Km) developed by BP as the operator to transport crude oil from the Azeri-Chirag-Guneshli oil field in the landlocked Caspian Sea to a marine shipping terminal (Haydar Aliyev) on the south-eastern Mediterranean coast of Turkey.
Construction Project
The APLNG pipeline project, a joint Venture between Origin Energy, ConocoPhillips, and Sinopec, was a high profile business investment to transport gas from the coal seam gas (CSG) fields in the Surat and Bowen basins in south western and central Queensland, Australia to a new Liquefied Natural Gas (LNG) processing facility located at Laird Point on Curtis Island, off shore Gladstone.
In February 2014, I was solicited by WorleyParsons to assist their tendering effort to secure the Engineering, Procurement and Construction Management (EPCM) services to TANAP, and after a period of successful negotiations in which I played an active role the contract was awarded to them in May.